Orono's Plowed Stretch of the Dakota Rail Trail Closes December 1. The Pipe Behind It Runs Into 2028.

Most of the Dakota Rail Regional Trail goes unplowed in winter. Three Rivers Park District plows the trail only where cities partner on maintenance. On the Dakota Rail, that means Minnetonka Beach, Spring Park, Wayzata, Orono, and the Mound section from County Road 110 to Seton Channel. "Other segments of the trail are not maintained."

Starting December 1, about two miles of that plowed Orono mileage closes, from North Shore Drive to Orono Orchard Road, and it stays closed through March 31. The closure is one piece of a new regional sewer line that will work its way through several Orono streets over the next two years.

A pipe that starts at Lilac Lane

The project behind the closure is the Metropolitan Council's Orono Interceptor 7113 Improvements. On the Met Council's project page, it's a new regional sewer pipe running from lift station L59 to Orono Orchard Road. The route, in order:

  1. From lift station L59 on Lilac Lane
  2. South on Old Crystal Bay Road
  3. East on North Shore Drive
  4. North on Brown Road
  5. Near Brown Road and Lakeview Avenue, onto the Dakota Rail Trail corridor
  6. Along the trail northeast to Orono Orchard Road

The trail closure covers the last two legs of that route. Old Crystal Bay Road, North Shore Drive and Brown Road carry the rest.

The reason for the work is age. The existing forcemain, line 7113, was built in 1979, serves lift station L59, and is nearing the end of its service life. The Met Council's capital program describes a full-length redundant forcemain plus rehabilitation of the existing line. It is a reliability project driven by the pipe's age, its condition, and the volume of flow it carries. So when the work is done, the area will have two lines where it now has one.

The job is substantial. In May 2026, the Met Council recommended Meyer Contracting Inc. for the construction contract as the low, responsive and responsible bidder, at a cost not to exceed $25,657,165.46.

One street at a time, into 2028

Building the line this way takes longer on purpose. The Met Council says it will use both open-trench and trenchless tunneled construction. The work will be sequenced so only one street is under construction at a time, which "can increase the project duration" but "helps avoid neighborhood disruption."

The published timelines don't quite agree, so the end date is best read as a range:

Source Start Finish
Met Council project page Late 2026 Spring/summer 2028
Met Council contract presentation, May 2026 Fall 2026 Substantial completion summer 2028, final completion fall 2028
Met Council capital program 2026 2029

On the street sections, the Met Council lists road closures, intersection restrictions and traffic detours, and says driveway access will be maintained. It also expects noise, dust, odors, vibration, visual impacts, and temporary wastewater conveyance pipes above ground while crews work.

The Met Council hasn't posted a street-by-street calendar. For now, the most direct way to know when Old Crystal Bay Road, North Shore Drive or Brown Road will be affected is the email and text sign-up on the project page. When the trail reopens, the sections disturbed by the sewer work will be repaved.

The trail this winter, end to end

The Orono closure isn't the only gap in the Dakota Rail this season, and as of the week this post goes up, it's the only one that hasn't started yet. Xcel Energy's work west of Mound closed its section on October 15.

Segment Status Dates Reason
Commerce Boulevard crossing, Mound Closed, posted detour From October 5 Hennepin County road project updating ramps to ADA standards
Shoreline Drive in Mound to Westonka Recreation Park in Minnetrista, about 2.5 miles Closed, no posted detour October 15 through end of February Xcel Energy transmission line replacement
Between the two closures, including Spring Park and Minnetonka Beach Open All winter
North Shore Drive to Orono Orchard Road, about 2 miles Closed, no posted detour December 1 through March 31 Met Council sewer line

Three Rivers says it scheduled both projects for fall and winter because "use of the trail decreases significantly during the winter months." For the Commerce Boulevard crossing, Three Rivers has posted a detour map.

The western closure runs past Gale Woods Farm. It belongs to a larger effort that the state's transmission planning report calls Rebuild 0735 St Bonifacius to Mound. That report says the line's structures are at the end of their life with numerous defects. It also points to forecast load growth, and expects that adding fiber-optic ground wire will mean replacing more than half the structures, in effect a full rebuild. The Laker Pioneer reported that construction would start this fall and continue through spring 2028. Kevin Coss of Xcel Energy told the paper:

"Most work will take place along the existing right-of-way. Property owners will receive advance notice of any activity affecting their property and may contact Xcel Energy with questions. While service interruptions are not expected, any brief planned outages will be communicated in advance."

Both projects run on longer clocks than the trail closures. The utility work in the corridor continues past spring. The trail closures are simply the part of each project scheduled for the season with the fewest trail users.

Where the plowed and groomed miles are instead

Three Rivers' Dakota Rail page says winter maintenance generally runs from mid-November through March. If this season follows that pattern, the Orono stretch will get about two weeks of plowing before it closes on December 1. After that, the closest options in town and nearby are mostly away from the lake corridor.

Luce Line State Trail. This is the nearest east-west trail in Orono itself. The Minnesota DNR directs hikers, skiers and winter bikers to the segment between Vicksburg Lane and Stubbs Bay Road, where snowmobiles aren't allowed. West of Stubbs Bay Road, the trail is groomed for snowmobiles, and those non-motorized users are barred. To reach the Long Lake parking lot, the DNR says to take Old Crystal Bay Road south to Watertown Road, go west to Stubbs Bay Road, then drive a quarter mile south to the lot on the west side of the road. Ungroomed skiing on the trail requires no Ski Pass, and no other trail fees apply. Old Crystal Bay Road is also on the sewer line's route, so it makes sense to check the Met Council updates before driving that way.

Baker Park Reserve. For skiers, Baker has 9.1 miles of cross-country trail groomed for both classic and skate skiing. Skiers 12 and older need a Three Rivers daily or annual ski pass. Three Rivers' posted 2026–27 prices are $12 for an all-parks daily pass, $8 for a natural-snow-parks daily pass, and $95 for a season pass. For anyone who isn't skiing, the Baker winter trailhead has a multi-use trail for hiking, snowshoeing, on-leash dog walking, skijoring, dog sledding and mountain biking. The campground road is plowed for walking and leashed dogs, which is the closest match here to a plowed trail walk.

Lake Minnetonka Regional Park. If what you want from the Dakota Rail is a walk near the lake, the regional park offers nearly a mile of plowed winter walking trail, plus snowshoeing. Snowshoes aren't allowed on ski trails unless signs say otherwise.

Gale Woods Farm. The farm's grounds are open daily from 5 a.m. to 10 p.m. It has ungroomed snowshoe trails and a farm store with posted daily hours. The barn opens only for scheduled programs. The farm sits along the closed Xcel segment, so plan to arrive by road rather than by trail this winter.

Wolsfeld Woods Scientific and Natural Area. Wolsfeld Woods is the least developed choice here. It has designated hiking trails, and the DNR lists snowshoeing and cross-country skiing among its activities.

When the Orono segment reopens after March 31, the repaved pavement will be the first finished result of a project that keeps going under nearby streets for another year or more.

If construction on Old Crystal Bay Road, North Shore Drive or Brown Road happens to fall in the same season you're planning to list or show a home, timing and presentation will matter. Jim Schwarz tracks projects like this across the north shore and can help you plan around them. Schedule a private consultation.